Inverter AC cable voltage drop calculator
Estimate inverter AC cable voltage rise or drop from entered current, phase, route length and cable data for Australian solar project records.
Vcable = F x I x Lkm x (R x PF + X x sin_phi); percent = Vcable / Vnominal x 100- Use the phase factor that matches the selected single-phase or three-phase AC run.
- Cable data must match the conductor, route and source basis entered by the user.
- The percent result is compared with the entered project target, not a universal DNSP outcome.
| Variable | Meaning | Unit | Use |
|---|---|---|---|
| F | Phase factor | factor | Use 2 for single phase and square root of 3 for three phase. |
| I | Inverter AC current | A | Entered directly or calculated from kVA or kW. |
| Lkm | One-way route length | km | One-way AC cable route length converted from metres. |
| R | Conductor resistance | ohm/km | Entered resistance from the project cable data source. |
| X | Conductor reactance | ohm/km | Entered reactance from the project cable data source. |
| PF | Power factor | ratio | Entered value used for kW current conversion and R/X impedance mode. |
| sin_phi | Reactive factor | ratio | Derived from power factor for impedance mode. |
| mV_per_A_m | Voltage-change data | mV/A/m | Alternative entered cable data where the source already matches the cable and circuit context. |
| Vcable | Cable voltage change | V | Calculated voltage rise or drop across the entered AC cable run. |
| Vnominal | Nominal AC voltage | V | Entered 230 V single-phase or 400 V three-phase project basis by default. |
| Margin | Target margin | % | Entered project target minus calculated voltage-change percent. |
More
Inverter AC cable voltage drop calculator technical guide
Estimate inverter AC cable voltage rise or drop from entered current, phase, route length and cable data for Australian solar project records.
Use this page when an inverter AC cable run needs a traceable voltage-rise or voltage-drop record before the result is carried into a cable schedule, quote review, commissioning pack or DNSP discussion. The calculation is only as strong as the inverter current basis, route length and cable data entered by the user.
The common solar question is not simply "what is the voltage drop?". For an exporting inverter, the practical issue is often voltage rise at the inverter end of the AC cable. The same cable formula gives the magnitude, but the record must say whether that magnitude is being added for export-rise review or subtracted for load-drop review.
Field use cases
| Work setting | Real question | Useful action from this page |
|---|---|---|
| Residential rooftop inverter | Does the AC run from a garage inverter to the switchboard create a voltage-rise estimate above the entered project target? | Enter inverter kVA or current, single-phase voltage, one-way route length and project cable data before finalising the run. |
| Commercial three-phase inverter | How close is the AC cable run to the entered voltage-rise target at the planned inverter current? | Compare voltage-change percent, target margin and maximum route length before documenting the cable schedule. |
| Quote or variation review | Is the longer route materially changing the cable discussion? | Use the same current and cable data with the revised route length so the effect is visible. |
| Commissioning record | Which assumptions were used when the inverter AC cable was checked? | Export the record with current basis, cable data source, route length and target attached. |
| DNSP or project review | Is the arithmetic ready to discuss, even though approval sits outside the calculator? | Keep the voltage-rise result separate from DNSP conditions, inverter settings and network voltage evidence. |
A useful inverter AC cable record is specific. "Voltage rise looks fine" is weak. "INV-AC-1, 5 kVA single phase, 20 m one-way route, 2.8 mV/A/m project cable data, 1.22 V rise, 0.53% against entered 1.0% target" can be reviewed and repeated when the route, inverter or cable data changes.
Inverter AC data checklist
| Value | Where it normally comes from | Why it matters |
|---|---|---|
| Inverter AC current | Inverter documentation, datasheet, schedule or project calculation | Current drives the cable voltage change directly. |
| kVA or kW rating | Inverter documentation or design schedule | Used only when current is not entered directly. |
| Phase arrangement | Installation design, switchboard schedule or inverter data | Sets the single-phase or three-phase voltage relationship. |
| Nominal voltage | Project basis, supply context or design note | Used to calculate voltage-change percent and endpoint voltage. |
| One-way AC route length | Cable route takeoff or site measurement | Longer routes increase voltage change directly. |
| mV/A/m or R/X cable data | Cable schedule, manufacturer data or project cable source | Determines the voltage-change value without copying controlled tables. |
| Project target | Project specification, design basis or reviewer instruction | The calculator compares against the entered target; it does not create a universal limit. |
Do not mix cable data from one conductor arrangement with a different route or installation assumption. If the source value is mV/A/m, it should already match the circuit context used by the project source. If the source gives resistance and reactance, enter both values and keep the source visible in the record.
Voltage rise and voltage drop interpretation
For an exporting inverter, the calculated cable voltage change is normally read as voltage rise toward the inverter terminals. The calculator adds the cable change to the entered nominal voltage and reports an estimated endpoint voltage. That value is a worksheet estimate, not a measurement of actual network voltage.
For load direction, the same cable magnitude is read as voltage drop. The calculator subtracts the cable change from nominal voltage. This is useful for a hybrid or backup context where the AC run is being reviewed in a load direction, but it should not be confused with the usual grid-export voltage-rise discussion.
The percentage result is often the most useful comparison value because it lets the same run be checked against the project target entered by the user. A negative target margin means the calculated percentage is above that target. That is not an automatic compliance outcome, but it is a practical stop point for route length, cable data, inverter current and project requirements.
Cable data source matrix
| Data mode | What the calculator does | When it is useful | Main risk |
|---|---|---|---|
| mV/A/m | Multiplies entered mV/A/m by current and one-way route length. | The project source already gives a voltage-drop/rise value for the selected cable context. | Using a value from the wrong conductor, arrangement or condition. |
| R/X impedance | Applies resistance, reactance, power factor and phase factor. | The project source gives conductor resistance and reactance values. | Entering resistance only when reactance matters, or using a power factor assumption without recording it. |
| kVA current basis | Converts apparent power to current before cable calculation. | Inverter apparent power is the clearest project value. | Assuming a rating equals the exact current used in every operating condition. |
| kW current basis | Converts real power with power factor before cable calculation. | The project basis is real power and the power factor assumption is explicit. | Hiding the power factor assumption or using a value not supported by the project record. |
The calculator deliberately does not embed a cable table. Cable data stays user-entered because Australian inverter AC cable checks depend on the selected cable source, conductor, insulation, installation method, grouping, ambient conditions, protection and project documentation.
Target review matrix
| Result condition | What it means in the worksheet | Practical action |
|---|---|---|
| Voltage change below entered target | The entered cable data, current and route length produce a percentage below the user's comparison value. | Keep the cable data source, target source and current basis with the record. |
| Voltage change close to entered target | Small changes in route, current or cable data may change the review. | Recheck measured route length, cable source and inverter current basis. |
| Voltage change above entered target | The worksheet exceeds the user's comparison value. | Review route length, conductor data, inverter current, phase arrangement and project requirements before relying on the run. |
| Endpoint voltage looks high | Export-rise arithmetic has been added to nominal voltage. | Do not treat the number as DNSP acceptance; check network voltage conditions and inverter requirements separately. |
| Cable source is uncertain | The formula may be correct but the data basis is weak. | Stop and obtain the correct cable data source before exporting the record. |
This matrix is not a compliance table. It is a review aid that helps identify which input is driving the result. Actual inverter operation can also be affected by network voltage, inverter settings, export limits, site loading, phase balance and DNSP requirements.
Review workflow
- Identify the inverter AC run reference from the cable schedule, switchboard schedule or drawing.
- Select export voltage rise unless the project is specifically reviewing load-direction voltage drop.
- Enter the phase arrangement and nominal voltage used in the project basis.
- Enter inverter current directly where available; otherwise enter kVA or kW with the power factor basis visible.
- Enter the one-way route length between the inverter and the connection point being checked.
- Enter cable data from the project source as mV/A/m or as resistance and reactance.
- Enter the project voltage-rise/drop target being used for comparison.
- Read the voltage-change percent, target margin and endpoint voltage together.
- If the margin is negative or narrow, review route length, cable data and current basis before changing documentation.
- Keep DNSP conditions, current standards, inverter manufacturer requirements and final cable selection as separate checks.
This workflow keeps the calculator as an arithmetic worksheet. It does not decide cable size, approve the connection point, set inverter controls or replace commissioning checks.
Worked records
| Situation | Inputs | Result | Record use |
|---|---|---|---|
| 5 kVA single-phase residential run | 230 V, 20 m one-way, 2.8 mV/A/m, 1.0% target | Current 21.74 A, voltage rise 1.22 V, 0.53%, endpoint 231.22 V | INV-AC-1: supplied cable data and 20 m route sit below the entered 1.0% project target. |
| 50 kVA three-phase commercial run | 400 V, 45 m one-way, R 0.387 ohm/km, X 0.08 ohm/km, 1.0% target | Current 72.17 A, voltage rise 2.18 V, 0.54%, endpoint 402.18 V | INV-COM-1: keep R/X source, phase basis and target source with the cable schedule. |
| Long single-phase route | 8 kVA, 230 V, 55 m one-way, 2.8 mV/A/m, 1.0% target | Current 34.78 A, voltage rise 5.36 V, 2.33%, endpoint 235.36 V | INV-LONG-1: voltage-rise estimate is above the entered target; review route, cable data and current basis before carrying forward. |
The examples show why route length and current basis matter. The calculation is not a generic solar answer; it is a record for one inverter AC cable run with a named source of cable data.
Boundary with neighbouring calculations
| Related task | Use this page? | Why |
|---|---|---|
| General cable voltage drop | Sometimes | Use this page only when the inverter/export context matters; use the general voltage-drop calculator for ordinary cable runs. |
| PV string voltage | No | PV string voltage is a DC module and temperature task handled by the PV string voltage calculator. |
| Battery DC cable voltage drop | No | Battery cable work is a high-current DC task with different voltage and product boundaries. |
| Inverter settings or export limit | No | Settings and limits depend on product, DNSP and commissioning requirements. |
| DNSP approval | No | DNSP requirements and connection outcomes sit outside this arithmetic worksheet. |
| Final cable selection | No | Current-carrying capacity, derating, protection and installation conditions require separate review. |
Keeping this boundary clear prevents the inverter AC cable worksheet from becoming a connection approval tool. The result shows whether the cable-run arithmetic is tidy enough to carry forward without pretending to close the project.
Australian context
Grid-connected inverter work in Australia sits inside current Australian standards, local authority requirements, DNSP conditions, network voltage conditions, equipment documentation and manufacturer instructions. AS/NZS 4777.1:2024 and AS/NZS 4777.2:2020 are relevant context for inverter energy systems, while AS/NZS 3008.1.1:2025 is relevant context for cable data and cable selection. DNSP service rules and connection processes can still govern the project outcome.
This page keeps the public calculation transparent. It does not reproduce controlled standards content, does not encode network-specific voltage-rise limits and does not state that an inverter run is acceptable. It records the arithmetic from the values entered by the user so the result can be reviewed with the proper project documents.
In practice, this record usually sits beside the inverter datasheet, cable schedule, switchboard schedule, site route measurement and connection-point documentation. The worksheet helps identify whether the cable-run arithmetic is worth carrying forward; it does not replace network voltage evidence, inverter settings review, current-carrying-capacity checks or manufacturer instructions.
| Record item | Why it matters |
|---|---|
| Inverter AC run reference | Ties the result to the inverter, switchboard schedule or drawing label. |
| Direction | Distinguishes export voltage rise from load-direction voltage drop. |
| Current basis | Shows whether the worksheet used entered current, kVA or kW with power factor. |
| Phase and nominal voltage | Confirms the 230 V or 400 V basis used for the percentage result. |
| One-way route length | Identifies the measured or estimated AC cable route used in the calculation. |
| Cable data source | Records whether mV/A/m or R/X values were taken from the project source. |
| Project target | Shows the comparison value used by the reviewer. |
| Target margin and endpoint voltage | Shows the practical review result without implying DNSP acceptance. |
| Reviewer | Identifies who prepared or checked the arithmetic record. |
Stop points
- The inverter AC current or rating basis is unknown.
- The one-way route length is estimated loosely and the result is close to the entered target.
- Cable data is copied from a different conductor, arrangement or installation assumption.
- The calculated percentage is above the entered project target.
- Endpoint voltage is being treated as a measured network voltage.
- DNSP connection requirements, export limits or inverter settings are being treated as optional.
- The result is being used as final cable selection without checking current-carrying capacity, protection, installation conditions and manufacturer instructions.
Single-phase residential inverter AC run
A 5 kVA single-phase inverter is reviewed over a 20 m one-way AC route using project-entered cable data of 2.8 mV/A/m.
- Review direction
- Export voltage rise
- Phase arrangement
- Single phase
- Inverter basis
- 5 KVA
- One-way route length
- 20 m
- Cable data
- 2.8 mV/A/m
- Current used21.74 A
- Export voltage rise1.22 V
- Endpoint voltage231.22 V
Maximum one-way route length at the entered target is approximately 37.8 m.
The voltage-rise estimate is below the entered project target, but cable data, inverter documentation and DNSP requirements still need review.
- 230 V single-phase inverter AC context.
- mV/A/m data is entered from the project cable data source.
- No DNSP approval, inverter-setting approval or final cable selection is made.
Three-phase commercial inverter AC run
A 50 kVA three-phase inverter is reviewed over a 45 m route using entered conductor resistance and reactance values.
- Review direction
- Export voltage rise
- Phase arrangement
- Three phase
- Inverter basis
- 50 KVA
- One-way route length
- 45 m
- Cable data
- 0.387 R, 0.08 X ohm/km
- Current used72.17 A
- Export voltage rise2.18 V
- Endpoint voltage402.18 V
Maximum one-way route length at the entered target is approximately 82.7 m.
The result is an impedance-based record for the entered commercial inverter run and should be kept with the cable data source and project target.
- 400 V line-to-line three-phase context.
- Balanced three-phase inverter output is assumed for the worksheet.
- Resistance and reactance values are entered project data.
Long single-phase route review
An 8 kVA single-phase inverter is checked over a 55 m one-way route to see whether the cable run exceeds the entered target.
- Review direction
- Export voltage rise
- Phase arrangement
- Single phase
- Inverter basis
- 8 KVA
- One-way route length
- 55 m
- Cable data
- 2.8 mV/A/m
- Current used34.78 A
- Export voltage rise5.36 V
- Endpoint voltage235.36 V
Maximum one-way route length at the entered target is approximately 23.6 m.
The voltage-rise estimate is above the entered project target. The next review should focus on route length, cable data, inverter current and project requirements.
- 230 V single-phase inverter AC context.
- The target is entered by the user and is not a universal compliance limit.
- No network voltage acceptance or DNSP approval is decided.