Submain voltage drop calculator

Check Australian submain or consumer mains voltage-drop allocation from demand current, route length, project cable data and upstream/downstream allowance.

  • Calculator
  • Cable sizing
  • Australia
Choose a common reference, or select Custom for the project switchboard, drawing or schedule label.
Use consumer mains only when that is the project run being reviewed.
Use line-to-neutral voltage for single phase and line-to-line voltage for three phase.
Use reviewed demand current where available, or convert kW/kVA for this allocation check.
A
Enter the demand current, real power or apparent power used for this run.
V
Defaults follow Australian 230/400 V supply context; edit only when the project basis differs.
m
Use the installed route length from source board to downstream board or consumer mains endpoint.
PF
Required for kW input and impedance mode; use project or equipment data where available.
%
Enter the project voltage-drop allowance used for this allocation review.
%
Enter voltage drop already used before this run.
%
Enter the allowance assigned to this submain or consumer mains segment.
%
Reserve allowance for final circuits or other downstream paths.
Choose whether project cable data is entered as mV/A/m or resistance/reactance.
mV/A/m
Enter the mV/A/m value for the reviewed conductor and circuit arrangement.
I = entered or converted demand current; Vd_submain = mV/A/m x I x L / 1000 or phase factor x I x Lkm x (R x PF + X x sin(arccos(PF))); Vdrop_submain_% = Vd_submain / Vnominal x 100; Vdrop_total_allocated_% = Vdrop_upstream_% + Vdrop_submain_% + Vdrop_downstream_reserved_%; remaining_downstream_% = total_allowance_% - Vdrop_upstream_% - Vdrop_submain_%; submain_margin_% = min(submain_allowance_%, total_allowance_% - Vdrop_upstream_% - Vdrop_downstream_reserved_%) - Vdrop_submain_%
  • The total allowance, upstream allowance and downstream allowance are entered project review values.
  • Demand current must come from a reviewed project source, maximum-demand worksheet, load schedule, equipment data or measured basis.
  • Cable voltage-drop data is entered by the user and must match the run being reviewed.
Formula variables
VariableMeaningUnitUse
IDemand current used for the runAEntered directly or calculated from kW or kVA.
Vd_submainCalculated voltage drop for this runVVoltage drop for the submain or consumer mains segment.
Vdrop_submain_%Run voltage-drop percentage%Calculated drop as a percentage of entered nominal voltage.
Vdrop_upstream_%Upstream drop already used%Allowance already used before this run.
Vdrop_downstream_reserved_%Downstream allowance reserved%Allowance held for final circuits or downstream load paths.
Vdrop_total_allocated_%Total allocated voltage drop%Upstream used plus calculated run drop plus downstream reserved allowance.
remaining_downstream_%Downstream remaining after this run%Allowance left after upstream used and this run are deducted.
submain_margin_%Run allowance margin%Available run allowance minus calculated run percentage.
More

Submain voltage drop calculator technical guide

Check Australian submain or consumer mains voltage-drop allocation from demand current, route length, project cable data and upstream/downstream allowance.

Field use cases

Use this calculator when the question is no longer just "what is the drop on this cable run?" but "how much of the project allowance does this run consume before the downstream circuits are checked?" That question comes up on multi-board installations, long runs to detached buildings, tenancy distribution boards, workshops, pump boards, commercial switchboards and consumer mains reviews where the route itself can take a large share of the available voltage-drop budget.

In practice the calculation often starts after another decision has already happened. A maximum-demand worksheet may have produced the current to use. A preliminary cable schedule may already list the proposed route. A drawing revision may have moved a board further away from the main switchboard. A contractor may be comparing whether a switchboard location is still workable after cable routes are measured on site. This page keeps the allocation arithmetic visible so those decisions do not become hidden inside a single voltage-drop number.

The output is most useful when the record travels with its basis: the run reference, demand current, cable data, route length, upstream value already used, downstream value reserved and total project allowance. Without those items the percentage can look precise while still being hard to review. The calculator deliberately does not decide the correct split. It shows the consequence of the split entered by the user.

Minimum export record

Submain allocation export record fields
Record fieldWhy it belongs in the exportExample
Project referenceConnects the allocation to the job, switchboard schedule or drawing revision.DB-A submain review
Run reference and typeIdentifies whether the record is for a submain or consumer mains run.DB-A-SUBMAIN, submain
Demand current basisShows the current used for the run voltage-drop calculation.100 A from maximum-demand worksheet
Route lengthKeeps the one-way cable path visible.80 m
Cable data basisShows the mV/A/m or R/X value used for the reviewed run.1.2 mV/A/m project cable data
Upstream usedRecords allowance already consumed before this run.0.5%
Run dropShows the calculated volts and percentage for this run.9.6 V, 2.4%
Downstream reservedKeeps final-circuit or downstream allowance visible.1.5%
Total allowance and marginSeparates the entered project limit from the calculated remaining allowance.5.0% total, 0.6% margin
ReviewerNames the person checking the arithmetic record.Electrician, engineer, estimator or reviewer

Keep the export concise. Longer project records for demand current, cable data, DNSP context, route measurement, AS/NZS 3008 review and final-circuit checks should remain in the project file rather than being folded into the calculator result.

Allocation data to confirm

Confirm the demand current before using the result. For a submain, the current may come from a maximum-demand worksheet, a load schedule, equipment information, a measured review, or a project value issued by the designer. For a consumer mains calculation, the basis can be more sensitive because network and supply conditions may also matter. The calculator accepts the demand value; it does not prove the demand basis is suitable.

Confirm the route length as the installed one-way cable path. Long routes often include vertical rises, switchroom offsets, tray changes, penetrations, service loops and termination allowances. A straight drawing measurement can understate the segment drop and leave too little allowance for final circuits.

Confirm the voltage basis before comparing percentages. A project schedule may use the nominal 230 V or 400 V basis, while a site note may record a measured voltage at a different point in the installation. Keep those as separate records if both are relevant. Do not calculate the voltage drop in volts from one basis and the percentage allocation from another.

Confirm cable data before choosing mV/A/m or impedance mode. The value must match the conductor, circuit arrangement, source document and operating basis being reviewed. A value copied from a different conductor, temperature basis or installation context can make the allocation look better or worse than the project record supports.

Confirm the upstream and downstream values as allocation entries, not as automatic rules. Upstream used is the voltage drop already consumed before this run. Downstream reserved is the allowance held for final circuits or downstream load paths after this run. If downstream circuits have already been calculated, use the reviewed value. If they have not, the reserve should come from the project basis and should not be hidden.

Allocation input checklist
ItemUse in the calculationStop if
Run referenceLinks the result to the switchboard, consumer mains, drawing or schedule item.The reference cannot be traced in the project record.
Demand currentSets the current used for the run voltage-drop calculation.The current is only a rough allowance and a reviewed basis exists elsewhere.
Voltage basisConverts the run voltage drop in volts into the percentage used for allocation.The record mixes nominal project voltage and measured site voltage without saying which basis is being reviewed.
Route lengthControls the length part of the voltage-drop formula.The length ignores known cable path changes or site allowances.
Cable dataSupplies mV/A/m or R/X values for the reviewed run.The data belongs to another conductor or source context.
Upstream usedCarries voltage drop already spent before this run.The upstream value is assumed but not recorded.
Downstream reservedProtects allowance for final circuits or downstream paths.Final circuits are ignored because the submain alone looks acceptable.
Total allowanceSets the review target entered by the user.The value is being treated as a universal result rather than a project basis.

Submain allocation matrix

The status is driven by allocation, not by the segment number alone. A run can have a modest percentage and still cause review if upstream drop and downstream reserve have already consumed the available budget. Conversely, a run can be below the total allowance but above the segment allowance assigned to that part of the installation.

Result status matrix
StatusWhat the arithmetic showsPractical review action
Allocation has marginUpstream used, calculated run drop and downstream reserved allowance remain within the entered total allowance.Carry the record forward with the demand source, cable data source and downstream checks attached.
Review run allocationThe calculated run drop is above the allowance left for this segment.Review route length, board position, cable data, demand basis and candidate cable workflow.
Review whole allocationThe combined upstream, run and downstream values exceed the entered total allowance.Review the split across the installation before changing only one circuit.
Review downstream allowanceUpstream and downstream values leave little or no usable allowance for this run.Recheck downstream circuit needs and whether the entered split is workable.

The receiving-end voltage at the end of the submain or consumer mains run is useful for documentation, but it should not be read on its own. A downstream board still feeds final circuits, equipment and sometimes future load. The better field question is whether enough allowance remains after this run for the circuits that follow.

Practical allocation decisions
Field conditionWhat to comparePractical response
Consumer mains already uses a large allowanceUpstream used plus consumer mains drop before any submain is added.Record the consumer mains basis first, then keep enough allowance for submains and final subcircuits instead of treating the first run as the whole installation.
Long submain consumes more than its segment allowanceCalculated run drop against the entered submain allowance and maximum length result.Review candidate cable data, route length, board location or whether the load should be supplied from a different distribution point.
Downstream final circuits need more allowance than expectedDownstream reserved allowance against final-circuit voltage-drop checks.Recheck the final subcircuits before accepting the submain allocation; a small submain margin can disappear after the longest final circuit is reviewed.
Nominal and measured voltage bases differPercentage calculated from the entered voltage basis.Keep one record for the project basis and another for the measured condition if required; compare like with like before resizing.
Total allocation is over the entered project targetUpstream used plus this run plus downstream reserved allowance.Review the distribution strategy: larger candidate cable, shorter route, relocated board, split distribution or a revised load basis may be more useful than changing only the final circuit allowance.

Worked Australian examples

A distribution-board submain is a typical allocation case. The reviewer has a 100 A three-phase demand current, an 80 m one-way route, entered cable data of 1.2 mV/A/m, a 400 V project basis, 0.5% upstream already used, 1.5% downstream reserved for final circuits and a 5.0% total project allowance. The calculator uses the mV/A/m formula:

  1. Run drop in volts: 1.2 x 100 x 80 / 1000 = 9.6 V.
  2. Run drop as a percentage of 400 V: 9.6 / 400 x 100 = 2.4%.
  3. Total allocation used: 0.5% upstream + 2.4% submain + 1.5% downstream = 4.4%.
  4. Total margin: 5.0% - 4.4% = 0.6%.
  5. Downstream remaining after this run: 5.0% - 0.5% - 2.4% = 2.1%.

That record has margin under the entered project allowance, but only because the downstream reserve has already been stated. It should still travel with the demand-current source, cable data source and final-circuit checks.

A long shed or workshop submain can create a different review condition. With the same 100 A, 80 m, 1.2 mV/A/m and 400 V basis, the run is still 9.6 V or 2.4%. If the project has entered only 1.8% as the submain segment allowance, with 0.2% upstream used and 0.4% downstream reserved, the total allocation is 3.0% and still below a 5.0% total target. The run itself is the problem: 2.4% is 0.6 percentage points above the entered segment allowance. The maximum length for a 1.8% run allowance at these entries is 60 m, so an 80 m route needs review before the result is carried forward.

A tenancy board can show the allocation trap. With 1.4% upstream already used, the same 2.4% submain drop and 1.4% downstream reserved, the total allocation is 5.2%. The submain drop may look ordinary on its own, but the combined record is 0.2 percentage points above the entered 5.0% project target. That is a distribution review problem, not a reason to quietly remove the downstream final-circuit allowance.

For a single-phase consumer mains record, the percentage changes with the voltage basis. A 63 A run over 45 m with entered data of 2.1 mV/A/m gives 5.95 V. On a 230 V project basis that is 2.59%. With 0.4% upstream entered and 1.6% downstream reserved, total allocation is 4.59% against a 5.0% target. If the same 5.95 V is reviewed against a measured 224 V basis, it becomes about 2.66%. The volts have not changed, but the percentage margin has tightened, which is why the voltage basis must be recorded.

Numeric allocation examples
ExampleEntered basisAllocation arithmeticPractical decision
DB-A submain with margin100 A, 400 V, 80 m, 1.2 mV/A/m, 0.5% upstream, 1.5% downstream, 5.0% total.Run drop 9.6 V = 2.4%; total used 4.4%; total margin 0.6%; downstream remaining after this run 2.1%.Carry forward with the demand source, cable data source and downstream final-circuit checks attached.
Long shed submain over segment allowanceSame 9.6 V and 2.4% run drop, but 1.8% run allowance, 0.2% upstream and 0.4% downstream.Total used is only 3.0%, but run margin is -0.6%; maximum length for the entered run allowance is 60 m.Review route length, board position, candidate cable data or load basis before changing the downstream reserve.
Tenancy board with whole-allocation pressureSame 2.4% run drop, with 1.4% upstream and 1.4% downstream reserved.Total used is 5.2%; total margin is -0.2%; downstream remaining after this run is 1.2%, below the 1.4% reserve.Review the split across consumer mains, submains and final subcircuits, or consider distribution changes.
Single-phase consumer mains voltage basis check63 A, 230 V, 45 m, 2.1 mV/A/m, 0.4% upstream, 1.6% downstream, 5.0% total.Run drop 5.95 V = 2.59% on 230 V; total used 4.59%; the same volts are about 2.66% on a 224 V measured basis.Record whether the project basis or measured basis is being reviewed before deciding whether to resize or reroute.
What changes the result
ChangeEffect on allocationTypical field consequence
Higher demand currentRaises the run voltage drop.Maximum-demand basis or load schedule may need review.
Longer routeRaises the run voltage drop.Switchboard location or cable route may become the limiting item.
Higher mV/A/m or impedanceRaises the run voltage drop.Candidate cable data or conductor selection workflow may need review.
More upstream usedReduces available allowance for this run and downstream circuits.Earlier consumer mains or submain records become important.
More downstream reservedReduces available allowance for this run.Final-circuit needs should be documented before the submain is accepted into the record.
Lower total allowanceTightens every segment of the allocation.The project target and the reason for it should be clear in the design record.
Lower voltage basisRaises the percentage for the same voltage drop in volts.Measured-voltage and project-voltage records should be compared separately.

Review workflow

  1. Establish the demand basis. Use the reviewed maximum-demand or load-schedule value where available, then keep the basis with the record.
  2. Confirm the route. Measure or review the installed one-way path from the source board to the downstream board or consumer mains endpoint.
  3. Enter cable data from the source that matches the run. Use mV/A/m when that data is available, or R/X values when impedance data is the project basis.
  4. Enter the allocation split. Record upstream used, downstream reserved and total allowance as project values rather than hidden assumptions.
  5. Keep the voltage basis visible. Use the nominal project basis or a measured basis consistently, and keep separate records if both are being compared.
  6. Read the result by margin. The run percentage, total allocated percentage, downstream remaining percentage and receiving-end voltage should be read together.
  7. Hand off the next task. Use the one-run voltage drop page for ordinary final-circuit checks, the cable size page for candidate screening, and the maximum-demand worksheet when the demand current itself needs review.

The record should state what changed when a result is reviewed. "Route length increased from 80 m to 110 m" is more useful than "voltage drop exceeded the entered allowance". "Downstream reserve increased after final-circuit review" is more useful than changing the submain target without explanation.

Boundary with voltage drop, cable sizing and maximum demand

This page sits between demand review and cable selection. It uses demand current, route length and cable data to show allocation pressure. It does not create the demand current, choose the cable, reproduce selection tables, check derating or coordinate protection.

Use the voltage drop calculator when the task is a single cable run without upstream and downstream allowance. Use the cable size calculator when a candidate metric cable needs to be screened against entered current-capacity and voltage-drop values. Use the maximum-demand worksheet when the demand current for a switchboard or load schedule needs to be assembled from entered rows.

Tool boundaries
RouteOwnsDoes not own
Voltage dropOne-run voltage-drop arithmetic from entered current or power, route length and cable data.Allocation across consumer mains, submains and final circuits.
Cable sizeCandidate cable screening from entered capacity and voltage-drop data.The upstream/downstream allowance split.
Submain voltage dropAllocation review for consumer mains or submain runs.Final cable selection, maximum demand and authority acceptance.
Maximum demandDemand-current worksheet from entered load rows and factors.Voltage-drop allocation or cable selection.

Stop points

  • Stop if the demand current cannot be traced to a suitable project basis.
  • Stop if the route length is a straight-line estimate and the installed route is known to be longer.
  • Stop if nominal project voltage and measured voltage are being mixed in one percentage comparison.
  • Stop if the cable data cannot be matched to the conductor, circuit arrangement and source document.
  • Stop if upstream drop has been assumed but not recorded.
  • Stop if downstream final circuits are ignored because the submain alone appears within the total allowance.
  • Stop if the total allowance is being treated as the calculator's rule rather than a user-entered project value.
  • Stop if the result is being used to select a final cable, calculate maximum demand, finalise consumer mains or close protection review.
  • Stop if current Australian requirements, DNSP or network requirements, manufacturer information or project documentation set conditions that have not been checked.

Distribution board submain with margin

A three-phase submain from the main switchboard to DB-A is reviewed at 400 V over an 80 m one-way route. The reviewer has reserved downstream allowance for final circuits and wants to see whether the submain allocation still has margin.

Run reference
DB-A SUBMAIN
Run type
Submain
Supply arrangement
Three phase
Nominal voltage
400 V
Demand basis
100 A
One-way route length
80 m
Cable data
1.2 mV/A/m
Total allowance
5%
Upstream used
0.5%
Downstream reserved
1.5%
  1. Demand current used100 A is used for the submain voltage-drop calculation.
  2. Run voltage drop9.6 V, or 2.4% of the entered nominal voltage.
  3. Total allocation0.5% upstream plus 2.4% for this run plus 1.5% downstream equals 4.4%.
  4. Remaining allowance0.6% remains against the entered total allowance. Downstream remaining after this run is 2.1%.
Allocation statusAllocation has margin

Run margin is 0.6%. Total margin is 0.6%.

The entered allocation has margin after upstream and downstream allowance are included. The result can be carried forward only with the demand-current source, cable data source and downstream final-circuit checks.

  • 400 V Australian three-phase context.
  • Demand current is entered from the project review basis.
  • Downstream final circuits still need their own voltage-drop checks.

Long shed submain requiring route review

A long three-phase shed submain uses a tight segment allowance because downstream final circuits are still reserved. The segment result is the limiting item even though the total allocation is not yet above the entered project limit.

Run reference
SHED SUBMAIN
Run type
Submain
Supply arrangement
Three phase
Nominal voltage
400 V
Demand basis
100 A
One-way route length
80 m
Cable data
1.2 mV/A/m
Total allowance
5%
Upstream used
0.2%
Downstream reserved
0.4%
  1. Demand current used100 A is used for the submain voltage-drop calculation.
  2. Run voltage drop9.6 V, or 2.4% of the entered nominal voltage.
  3. Total allocation0.2% upstream plus 2.4% for this run plus 0.4% downstream equals 3%.
  4. Remaining allowance2% remains against the entered total allowance. Downstream remaining after this run is 2.4%.
Allocation statusReview run allocation

Run margin is -0.6%. Total margin is 2%.

The run voltage drop is above the allowance left for this segment. Review the route, board position, cable data source, demand basis or candidate cable before relying on the allocation.

  • The entered 1.8% segment allowance is a project review value.
  • Cable data is entered by the user and is not selected from a table by this calculator.
  • The result does not decide a final cable size.

Tenancy submain with downstream allowance pressure

A tenancy distribution board has upstream voltage drop already recorded and downstream circuits still reserved. The submain by itself appears reasonable, but the combined allocation exceeds the entered project target.

Run reference
TENANCY-SUBMAIN
Run type
Submain
Supply arrangement
Three phase
Nominal voltage
400 V
Demand basis
100 A
One-way route length
80 m
Cable data
1.2 mV/A/m
Total allowance
5%
Upstream used
1.4%
Downstream reserved
1.4%
  1. Demand current used100 A is used for the submain voltage-drop calculation.
  2. Run voltage drop9.6 V, or 2.4% of the entered nominal voltage.
  3. Total allocation1.4% upstream plus 2.4% for this run plus 1.4% downstream equals 5.2%.
  4. Remaining allowance-0.2% remains against the entered total allowance. Downstream remaining after this run is 1.2%.
Allocation statusReview whole allocation

Run margin is -0.2%. Total margin is -0.2%.

The allocation should be reviewed as a whole. The combined upstream, submain and downstream values are above the entered project target, so changing only the final-circuit assumption may not solve the issue.

  • The upstream value is entered from an existing project record.
  • The downstream reserve is retained for final-circuit review.
  • The result is an allocation review, not a DNSP or service-acceptance decision.

Questions

Is this different from the voltage drop calculator?

Yes. The voltage drop calculator checks one run. This page checks how a submain or consumer mains run fits inside an upstream and downstream allocation split.

What demand current should I enter?

Use a reviewed demand current where available, such as a maximum-demand worksheet value, load schedule value, equipment data or measured basis suitable for the project.

Does this choose the cable size?

No. It checks allocation from values entered by the user. Cable selection, current capacity, installation method, derating, protection and project documentation remain separate tasks.

How much downstream allowance should I reserve?

The calculator does not decide the split. Enter the allowance used or reserved by the project basis, then check final circuits separately.

Can this be used for consumer mains?

It can record a consumer mains allocation calculation when the project basis is entered by the reviewer, but it does not provide supply authority or DNSP acceptance.